Population growth can really put a strain on a community's infrastructure and the remedies are often very costly.

 

One of our clients faced this situation when their elevated tank became hydraulically locked-out due to the rapid growth of their city. Proposed solutions included raising the tank or building a new tank--both expensive projects. 

 

HIGHFILL was brought on board and determined that a 1.5 MGD packaged pump station would sufficiently increase the presssure to feed the system at a fraction of the cost of the other recommendations.

 

The end result was a happy client with extra money to spend on their growing city. We call that a win-win!

 

 